Emergency Planned Maintenance CH-008814 - 3BRA and 3HRS NBN POI(s)
Scheduled Maintenance Report for FSG
Completed
The scheduled maintenance has been completed.
Posted Apr 16, 2024 - 04:00 AEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 16, 2024 - 00:00 AEST
Scheduled
Change ID: CH-008814

Emergency Maintenance Window:
======================
Start Date & Time: 16/04/2024 00:00:00 AEST
Finish Date & Time: 16/04/2024 04:00:00 AEST

Impact
======================
Service Impact: Up to 4 hour service interruption within a 4 hour emergency maintenance window.

Summary
======================
FSG engineers have been notified by our backhaul provider that they need to perform emergency maintenance on the equipment servicing the following NBN POI(s):
- 3BRA (Ballarat)
- 3HRS (Horsham)


During the emergency maintenance window customers will experience a service interruption to the impacted POI(s) after which service will restore.

Our NOC will monitor this work closely and send an additional advisory should the emergency maintenance be unsuccessful or have to be rolled back.


Kind Regards,

FSG NOC
E: support@fieldsolutions-group.com
W: www.fieldsolutions-group.com
Posted Apr 15, 2024 - 15:42 AEST
This scheduled maintenance affected: VIC NBN POIs (Backhaul - NBN POI, NBN POI - 3BRA (Ballarat), NBN POI - 3HRS (Horsham)).